BPC-070 Geotechnical Waiver Request
Version: 06/17/2026
Purpose
The purpose of this handout is to describe the applicable submittal and justification required for applicants to request a waiver to the geotechnical report requirements of the California Building Code (CBC) Chapter 18.
Technical Details
Background
The determination of requiring a project specific geotechnical report is made in accordance with the Permit Sonoma Technical Bulletin B-28 When is a Geotechnical Investigation Required? and Policy 4-0-2 Building Site Evaluation. This document outlines the justification and verification items that shall be submitted in order for Permit Sonoma to consider waiving the requirement for a full geotechnical investigation and report prepared in accordance with CBC Section 1803.6.
Submittal Requirements
The applicant shall upload the following items to justify that either geotechnical hazards do not exist in the area(s) of work, or that all applicable geotechnical hazards have been adequately mitigated in the proposed design and/or field inspection protocol.
- A written request prepared by the California licensed design professional in responsible charge, e.g. engineer or architect. The request shall be sealed, signed, and dated in accordance with the California Business and Professions Code and shall include the following information:
- Identify that the individual requesting the waiver has visited the site and reviewed any previously prepared geotechnical reports applicable to the project site.
- Date(s) of site visit(s) shall be provided and must have occurred within 6 months of the date the waiver request is being considered.
- Identify if the design professional concurs with recommendations and observations made in any previously prepared geotechnical reports.
- Identify and describe the soil material(s) in the area(s) of proposed development, in accordance with CBC Section 1803.5.1.
- Provide a classification of the soil material(s) in accordance with American Society for Testing and Materials (ASTM) D2487.
- Identify and describe any evidence of questionable soil onsite, in accordance with CBC Section 1803.5.2.
- Identify if existing structures exhibit signs of underlying soils of low bearing capacity.
- Identify if load bearing values in the proposed design exceed presumptive values specified in CBC Table 1806.2.
- Identify if expansive soil is present in the underlying soils, in accordance with CBC Section 1803.5.3.
- If expansive soils are present, adequate design and construction provisions shall be identified to demonstrate all adverse effects have been mitigated.
- Identify if there is evidence of high ground water table, in accordance with CBC Section 1803.5.4.
- Identify if deep foundations are proposed in the design, in accordance with CBC Section 1803.5.5.
- If deep foundations are proposed, identify and justify the methodology of determining applicable design criteria.
- Identify structural observation and special inspection requirements that will be included in an accompanying Statement of Special Inspection.
- Identify if there are indications of issues associated with doubtful characteristics in the subsurface rock strata, as required by CBC Section 1803.5.6.
- Identify if there will be excavations that will reduce support from any existing foundation, as required by CBC Section 1803.5.7.
- Identify if any shallow foundations will bear on compacted fill more than 12 inches in depth, as required by CBC Section 1803.5.8. Any existing or proposed fill shall be adequately specified and verified as identified below.
- Provide specifications for the preparation of the site prior to placement of compacted fill material.
- Provide specifications for material to be used as compacted fill.
- Identify test methods to be used to determine the maximum dry density and optimum moisture content of the material to be used as compacted fill.
- Identify the maximum allowable thickness of each lift of compacted fill material.
- Identify the field test method for determining the in-place dry density of the compacted fill.
- Identify the minimum acceptable in-place dry density expressed as a percentage of the maximum dry density.
- Identify the number and frequency of field tests required to determine compliance with required compaction percentage.
- Provide a completed Statement of Special Inspections identifying the continuous observation and testing of proposed fill placement and compaction, as required by CBC Section 1705.6.
- Identify if shallow foundations will bear on fill of controlled low-strength material, in accordance with CBC Section 1803.5.9.
- Identify if a proposed structure will be placed on a slope exceeding 33.3-percent, or if a structure will be placed near an ascending or descending slope surface, as required by CBC Section 1803.5.10.
- Adequate documentation and dimensions shall be provided that justifies setbacks from an ascending or descending slope surface that meet setback and clearance requirements of CBC Section 1808.7.
- Alternate setback and clearance recommendations shall be provided to demonstrate that the intent of CBC Section 1808.7 would be satisfied.
- Alternate setback recommendations shall include consideration of material, height of slope, slope gradient, load intensity, and erosion characteristics of slope material.
- Identify if conditions indicate potential hazards of slope instability, liquefaction, differential settlement, or surface rupture due to fault spreading, as required by CBC Section 1803.5.11.
- Identify if foundation walls, basements, or retaining walls supporting more than 6 feet are proposed, as required by CBC Section 1803.5.12.1.
- Provide a determination of dynamic seismic lateral earth pressures on foundation walls and retaining walls supporting more than 6 feet of backfill height due to design earthquake ground motions.
- Identify the potential, consequences, and mitigation measures of liquefaction and soil strength loss evaluated for site peak ground acceleration, as required by CBC Sections 1803.5.12.2, 1803.5.12.3, and 1803.5.12.4.
- Identify if the project includes work within the minimum stream setback distance from the top of bank, as outlined in the Sonoma County Code (SCC) Section 7-14(c).
- The request shall also include a discussion and analysis of any past geotechnical reports prepared at the proposed project site.
- Identify that the individual requesting the waiver has visited the site and reviewed any previously prepared geotechnical reports applicable to the project site.
- Any geotechnical related items that are proposed to be verified, observed, or tested during construction shall be adequately documented in CNI-033-Statement-of-Special-Inspections (PDF). Agencies or individuals performing geotechnical special inspections, testing, or observations shall be on the pre-approved CNI-014 Special Inspection Agency Recognition List, or adequate information regarding independence, qualifications, equipment, and education of the proposed individual or agency proposing to perform special inspections shall be provided for evaluation and approval, in accordance with CBC Section 1703.1.
Evaluation and Determination
The geotechnical waiver request documentation and justification submitted shall be reviewed by Permit Sonoma Building Division staff, typically within 10 business days from the date of submittal. Hourly review fees shall be assessed for the review of the request in accordance with the currently adopted fee schedule. If accepted, all proposed mitigation measures and recommendations shall be adequately identified and detailed in the applicable project plans, calculations, and other supporting documents. Plans and supporting documents will be reviewed for code compliance in further detail during the Building Plan Check review and approval process which typically occurs within 30 business days from the date of acceptance of the geotechnical waiver request or submittal of a complete application, including a project specific geotechnical report if the waiver request is not approved.